Began operating solar power plant in Gabela

Began operating solar power plant in Gabela

In Gabela, Capljina municipality, was put into operation a solar power plant by the company Solar energy d. o. o. from the Capljina, writes Vecernji.

It is a photovoltaic power plant, as the opening drive solar power plant in Gabela pointed out, one of the largest in Bosnia and Herzegovina.

Solar power

The panels are spread over 6,500 square meters, and the planned annual production is 1.5 million kilowatt-hours (kWh). The whole plant covers an area of ​​16,800 meters.

It is interesting that the first solar power plant in the Capljina municipality to reduce carbon dioxide emissions by 1,318.574 kilograms annually.

Commenting on the project and its implementation, Andrija Obad, one of the investors, says:

– The company whose main purpose is the production of energy from renewable sources we established in 2010.

When we comprehend the legal possibilities, we headed to the realization, however, it’s been six years until we presloženoj legislation failed to obtain all the necessary permits, and then build the facility, says Andrija Obad, one of the investors in the solar power plant Capljina Gabela local community and highlights :

– The power plant is a 1 megawatt (MW)

To my knowledge, this is one of the largest, if not the largest, power plants of this kind in Bosnia and Herzegovina.

The building occupies an area of ​​less than 17 acres, and its construction lasted three months.

Among other things, built the 3,800 panels made in Germany, said Andrija Obad noting that the newly opened solar power plant in Gabela in electricity production equivalent of 1,500 tons of carbon dioxide to the atmosphere discharges fossil fuels.

Investors in power

The construction of the plant above the Price’s “Troy” in Capljina local community Gabela, investors Andrija Obad, Gordan Bakalar and Davor Jovic invested 2.8 million KM.

As the opening ceremony of the solar power plants, among other things, pointed out, the role of the return expected for eight to nine years, while the power plant should work about 35 years ago.

Renewable Energy Projects in Bosnia and Herzegovina

Leave a Comment

Your email address will not be published. Required fields are marked with *

Cancel reply